Minutes of the Booster Corrector Prototype Test Planning Meeting

Document #:
Beams-doc-2792-v7
Document type:
Minutes
Submitted by:
Craig C Drennan
Updated by:
Craig C Drennan
Document Created:
29 May 2007, 13:15
Contents Revised:
05 Jul 2007, 14:21
Metadata Revised:
05 Jul 2007, 14:21
Viewable by:
  • Public document
Modifiable by:

Quick Links:
Latest Version

Other Versions:
Beams-doc-2792-v6
02 Jul 2007, 12:27
Beams-doc-2792-v5
02 Jul 2007, 12:26
Beams-doc-2792-v4
11 Jun 2007, 09:29
Beams-doc-2792-v3
04 Jun 2007, 07:58
Beams-doc-2792-v2
04 Jun 2007, 07:56
Beams-doc-2792-v1
29 May 2007, 13:16
Abstract:
Introduction:
We are planning to do a pre-shutdown installation of a new corrector package into the booster. This would test not only the corrector package but all of the other associated power supplies and controls. By putting the corrector package into the path of the beam we will be able to get an early indication of how this new system will impact the beam. Below are the minutes of each meeting so far. We expect to meet each Friday at 1:00 in the Penthouse.