PIP I: RFQ Injector

Document #:
Beams-doc-4563-v2
Document type:
Talk
Submitted by:
Cheng-Yang Tan
Updated by:
Cheng-Yang Tan
Document Created:
25 Mar 2014, 07:52
Contents Revised:
25 Mar 2014, 08:43
Metadata Revised:
25 Mar 2014, 08:43
Viewable by:
  • Public document
Modifiable by:

Quick Links:
Latest Version

Other Versions:
Beams-doc-4563-v1
25 Mar 2014, 07:52
Abstract:
The RFQ injector has replaced the Cockcroft-Walton accelerator has been operational since December 2012. The journey from testing, validation to installation and operations had been an interesting one because problems were found and had to be fixed before the injector could be installed. This talk will examine the problems and fixes that were applied to get the RFQ ready for installation as well as some problems that have occurred and their fixes during operations for the past year.
Files in Document:
Keywords:
RFQ Injector