FRIB linac commissioning

Document #:
Beams-doc-8428-v1
Document type:
Talk
Submitted by:
Rob Ainsworth
Updated by:
Rob Ainsworth
Document Created:
26 May 2020, 10:26
Contents Revised:
26 May 2020, 10:26
Metadata Revised:
26 May 2020, 10:26
Viewable by:
  • Public document
Modifiable by:

Quick Links:
Latest Version

Abstract:
Recently we demonstrated threshold Key Performance Parameter of the FRIB linac system by acceleration of Ar-36 ion beam up to 204.4 MeV/u. The staged commissioning of the linac started in 2017 with beam acceleration in the CW RFQ and continued in following years by acceleration of argon beam to 2 MeV/u in 2018, to 20 MeV/u in 2019 and KPP energy of 200 MeV/u was achieved on March 19, 2020 by using only 251 SC cavities out of 324. The beam commissioning periods were very short to allow completion of hardware installation in the tunnel. This talk will present status of accelerator systems prior to and during the commissioning, beam tuning procedures, beam measurements and main results of each commissioning stage.
Files in Document:
DocDB Home ]  [ Search ] [ Last 20 Days ] [ List Authors ] [ List Topics ] [ List Events ]

DocDB Version 8.8.9, contact Beams Document Database Administrators